Capital Projects Status
The following is a summary list of active Capital Improvement Projects within the city limits of Hoover. As individual projects progress, their status will be updated. As projects are completed, they will be removed from the list.
ALL PROJECTS AS OF SEPTEMBER 28, 2023
Project Type | Lead Agency | Status | Current Status (% Complete) |
Next Milestone | Next Milestone (Target Date) |
---|---|---|---|---|---|
ROADWAYS |
|||||
Valleydale Rd Widening (Little) - Widens Valleydale Rd from Riverchase Pkwy to Business Center Drive |
ALDOT | ROW Acquisition | 30% | Bid Process | 2024 |
Valleydale Rd Widening (Big) - Widens Valleydale Rd to five lanes from Caldwell Mill Rd to Hwy 280. | ALDOT | ROW Acquisition 94 Total tracts 3 Pending |
95% | Utility Coordination | 2023 |
South Shades Crest Rd, Additional Northbound Lane - Adds a northbound lane on South Shades Crest Road from Willow Lakes Drive to Hwy 150. | Jefferson County | Preliminary Design | 90% | Construction | Summer 2024 |
Galleria Blvd Extension - County led project that extends Galleria Blvd by Chick-Fil-A to Old Montgomery Highway | Jefferson County | Right of Way Acquisition | 80% | Construction | 2023 |
Exit 9 Interchange | City of Hoover/ ALDOT |
Preliminary Design | 30% | Bid Process | 2025 |
SIDEWALKS,GREENWAYS & TRAILS |
|||||
Chapel Rd Sidewalks - Extend sidewalk from Matzek Drive to Park Ave. (See more info.) | ALDOT | Construction |
80% | Completion | Winter 2023 |
US Hwy 150 Sidewalk - Provides sidewalk on one side of Hwy 150 from Hwy 31 to Cahaba River Estates. | ALDOT | Design & Planning | 90% | Right of Way Acquisition | TBD |
Alford Avenue Sidewalks - Phase 1 - Constructs sidewalks along Alford Avenue from Haden Street to Pine Lane and Haden Street from Alford Avenue to Blue Ridge Blvd. | City of Hoover | Final Design Stages | 95% | Right of Way Acquisition | TBD |
Old Columbiana Road Sidewalks - Patton Chapel Road to Green Valley Elementary | City of Hoover | Construction | 5% | Completion | Spring 2024 |
Al Seier Road Sidewalks - East of Sulphur Springs Road to Ball Park | City of Hoover | Design Stage | 95% | Bid Process | Fall 2023 |
Sulphur Springs Road Sidewalks - Preserve Parkway to Al Seier Road | City of Hoover | Design Stage | 95% | Bid Process | Fall 2023 |
GENERAL / MISC. |
|||||
Gwin/Simmons Traffic Signal Installation | City of Hoover | Construction | 10% | Completion | Fall 2023 |
Hwy 31 at Hendrick/Hoover Commons Traffic Signal Upgrades | City of Hoover | Construction | 5% | Completion | Fall 2023 |
Hwy 150 at ATI Pkwy Traffic Signal Installation | City of Hoover | Permitting | 50% | Construction | Fall 2023 |
Hwy 31 at Patton Chapel North Traffic Signal Upgrades | City of Hoover | Construction | 5% | Completion | Fall 2023 |
Upgrade Woodford Pump Station | City of Hoover | Construction | 15% | Completion | Spring 2024 |
Applecross Pump Station Replacement | City of Hoover | Construction | 50% | Completion | Winter 2023 |
Maiden Lane - Replace double 36" CMP with 36 ft. of double 36" RCP and replace two headwalls | City of Hoover | Construction | 5% | Completion | Winter 2023 |
Pickleball Courts @ Veterans Park | City of Hoover | Construction | 10% | Completion | Summer 2024 |
Lake Forest Dam Rehabilitation | City of Hoover | Construction | 30% | Completion | Fall 2025 |
Hoover Met Parking Lot | City of Hoover | Design Stage | 90% | Construction | Winter 2023 |