Capital Improvement Projects

The following is a summary list of active Capital Improvement Projects within the city limits of Hoover.  As individual projects progress, their status will be updated.  As projects are completed, they will be removed from the list. 


ALL PROJECTS AS OF APRIL 6, 2021

Project Type Lead Agency Status Current Status (% 
​Complete)
Next Milestone Next Milestone (Target Date)

ROADWAYS

         
Patton Chapel Road Improvement - Modifies two existing intersections into one, in front of Gwin Elementary School. Extends sidewalk along Patton Chapel Rd.  For additional information on this project, contact Jefferson County Roads
​and Transportation at (205) 325-5141. (See More Info.)
Jefferson County Construction   Completion of    Roadway Improvements
Summer 2021
Valleydale Rd Widening (Little) - Widens Valleydale Rd from Riverchase Pkwy to Business Center Drive
ALDOT Design 95% ROW Acquisition ROW Acquisition To Start 2021
Valleydale Rd Widening (Big) - Widens Valleydale Rd to five lanes from Caldwell Mill Rd to Hwy 280. ALDOT ROW Acquisition
​94 Total tracts
​6 Pending​
87% Utility Relocation       2021
South Shades Crest Rd, Additional Northbound Lane - Adds a northbound lane on South Shades Crest Road from Willow Lakes drive to Hwy 150.                Jefferson County      Permitting Process 95% Construction TBD - Coordinating efforts with Jefferson County & CSX Railroad

SIDEWALKS, GREENWAYS & TRAILS

         
Chapel Rd Sidewalks - Extend sidewalk from Matzek Drive to Park Ave.  (See more info.) ALDOT ROW Acquisition
​30 Total tracts
​ 
100% Plans Prepared To Be Bid by ALDOT 07/21
US Hwy 150 Sidewalk - Provides sidewalk on one side of Hwy 150 from Hwy 31 to Cahaba River Estates. ALDOT Design & Planning  70% ROW Acquisition TBD
Bluff Park Sidewalks - Constructs sidewalks on multiple streets in Bluff Park. (See More Info.)
ALDOT Construction 98% Completion - Working On
​Punch List Items
04/21
Inverness Community Greenway - Constructs sidewalk and trail along Inverness Parkway from Valleydale Rd, through the City's Inverness Nature Park. ALDOT Construction
10% Completion Fall 2021

GENERAL / MISC

.
         
US Hwy 31 Street Light Replacement, Phase 2 - Installs new street lighting along Hwy 31 from Patton Chapel Rd to I-65. ALDOT Design

99% Final Plans Submitted To ALDOT For Bidding 
 Summer 2021
Inverness WWTP Filter Rehab
​ Repairs Existing Filters
City of Hoover Construction 90% Completion 05/21